Christian Brook Sewer Separation Contract 1 - Week of January 9 - January 13 
P. Gioioso & Sons will continue installation of drainage piping during the week of January 9th thru January 13th.
Crew #1: Will continue to excavate and install 60” diameter Drain piping on North Street between Maple Street and Oak Street. The Maple Street detour will remain in effect during working hours.
Crew #2: Will continue hammering ledge and installing catch basins on North Street. As time permits, the crew will dig test pits to locate utilities at various locations.
Crew #3: Advance Drilling and Blasting will not be on site this week.
In support of the project, Liberty Utilities and RH White will continue relocating the gas mains on Salmon Street and Smyth Road; and complete relocating the gas main on Oak Street and North.