Manchester, NH: City
Monday November 28th, 2022 :: 08:30 a.m. EST

Advisory

Christian Brook Sewer Separation Contract 1 - Week of November 28 - December 2

P. Gioioso & Sons will continue installation of drainage piping during the week of November 28th  thru December 2nd .

Crew #1: Will continue installation catch basins and drain piping at the Ash Street and North Street intersection.

Crew #2:  Will continue installing catch basins on North Street between Ashland Street and Dallaire Street and catch basins on Dallaire Street.

Crew #3: Advance Drilling and Blasting will continue drilling and blasting ledge in Maple Street at the intersection of North Street.

Maple Street will be detoured around the North Street intersection during working hours Monday through Friday to allow continuation of blasting ledge for the main line drain pipe installation.