Community
Northwest Resiliency Park
Construction continues on the 5-acre Northwest Resiliency Park, which will be New Jersey’s largest resiliency park. The park will have above and below ground infrastructure to withhold up to 2 million gallons of rainwater to help mitigate local flooding. The following activities are anticipated this week:
Construction updates on water mains, Northwest Resiliency Park
Water main repair on Willow Avenue
Repairs to the water main on 14th and Willow Avenue have been completed, and the roadway is anticipated to be fully open to traffic by this evening.
Water Infrastructure Upgrades
The City continues with the first phase of its water main replacement project, which will replace a total of 15 blocks, or 7,000 linear feet of Hoboken’s oldest water mains. The following activities are anticipated this week:
- Monday 2/17/2020: No construction in observance of Presidents Day.
- Tuesday 2/18/2020: Garden Street between Observer Highway and 2nd Street will be closed at times between the hours of 8 AM - 4 PM for installation and transfer of water services. There will be temporary service interruptions for individual residents for up to an hour during the water service turnover. Each affected building will be notified by posting on the door.
- Tuesday 2/18/2020: Jefferson Street between 8th and 9th Streets will be closed at times between the hours of 8 AM - 4 PM for installation and transfer of water services. There will be temporary service interruptions for individual residents for up to an hour during the water service turnover. Each affected building will be notified by posting on the door.
- Tuesday 2/18/2020 - Thursday 2/20/2020: Jefferson Street between 10th and 11th Streets will be closed at times between the hours of 8 AM - 4 PM for installation of the new water main.
- Thursday 2/20/2020 - Friday 2/21/2020: Jefferson Street between 8th and 9th Streets, and 8th Street between Adams and Madison Streets will be closed at times between the hours of 8 AM - 4 PM for shut down of an old main. There will be temporary service interruptions for individual residents for up to four hours during the water service turnover. Each affected building will be notified by posting on the door.
- Wednesday 2/19/2020 - Friday 2/21/2020: Bloomfield Street between 3rd and 4th Streets will be closed at times between the hours of 8 AM - 4 PM for installation of the new water main.
- Wednesday 2/19/2020 and Friday 2/21/2020: Monroe Street between 3rd and 4th Street will be closed at times between the hours of 8 AM - 4 PM for installation of the new water main.
Northwest Resiliency Park
Construction continues on the 5-acre Northwest Resiliency Park, which will be New Jersey’s largest resiliency park. The park will have above and below ground infrastructure to withhold up to 2 million gallons of rainwater to help mitigate local flooding. The following activities are anticipated this week:
- Monday 2/17/2020: No construction in observance of Presidents Day.
- Tuesday 2/18/2020: Garden Street between 1st Street and 2nd Street will be closed at times between the hours of 8 AM - 4 PM while the old water main is being abandoned. No water service interruptions are anticipated.
- Tuesday 2/18/2020: Jefferson Street between 8th and 9th Streets will be closed at times between the hours of 8 AM - 4 PM for installation and transfer of water services. There will be temporary service interruptions for individual residents for up to an hour during the water service turnover. Each affected building will be notified by posting on the door.
- Tuesday 2/18/2020 - Thursday 2/20/2020: Jefferson Street between 10th and 11th Streets will be closed at times between the hours of 8 AM - 4 PM for installation of the new water main. The intersection of Jefferson and 11th will be closed for excavation and installation of water main casing work.
- Thursday 2/20/2020 - Friday 2/21/2020: Jefferson Street between 8th and 9th Streets, and 8th Street between Adams and Madison Streets will be closed at times between the hours of 8 AM - 4 PM for shut down of an old main. There will be temporary service interruptions for individual residents for up to four hours during the water service turnover. Each affected building will be notified by posting on the door.
- Wednesday 2/19/2020 - Friday 2/21/2020: Bloomfield Street between 2nd and 3rd Streets will be closed at times between the hours of 8 AM - 4 PM for installation of the new water main.
- Wednesday 2/19/2020 and Friday 2/21/2020: Monroe Street between 3rd and 4th Street will be closed at times between the hours of 8 AM - 4 PM for installation of the new water main.