City of Alameda Public Works: Traffic Advisory
City of Alameda Public Works anticipates traffic impacts due to Park St./Blanding Avenue Paving Project (Project).
Project will begin on Sunday November 4 at 7pm and is scheduled to be completed on Friday November 9 (weather/schedule permitting). City contractors will be applying asphalt concrete overlays along portions of the north end of Park Street between Blanding Avenue and Buena Vista Avenue and along Blanding Avenue between Oak and Broadway. If travelling in the area, please allow extra time and/or use alternate routes.
During construction, portions of Park Street and Blanding Avenue may be reduced to one lane of traffic. Emergency Vehicles will continue to have access and staff will make all reasonable attempts to keep adjacent driveways accessible to residents, employees and customers. It is possible that on-street parking may also be restricted during construction hours.
Project Schedule (weather permitting):
- Sunday (11.04.2018)
- 7:00 PM to 5:00 AM
- Park St. between Blanding Ave. and Eagle Ave.
- Monday (11.05.2018)
- After 5:00 AM No construction related traffic impacts anticipated
- Tuesday--Friday (11.06.2018-11.09.2018)
- 9:00AM-3:00PM daily
· Park St. between Eagle Ave. and Buena Vista Ave.
· Blanding Ave. between Oak and Park St.
· Blanding Ave. between Park St. and Broadway
NOTE: construction will not necessarily occur in above order nor will all locations be affected at all times, but areas within above roadways may experience project impacts/ traffic delays during construction.
For Full details, view press release HERE