Receive alerts from your local agencies
...or text your ZIP CODE to 888777 for mobile alerts

Full Notification

Clearlake PD
Monday August 20th, 2018 :: 11:11 a.m. PDT

Community

PUBLIC NOTIFICATION OF CONSTRUCTION COUNTRY CLUB DRIVE & KINGS LANE REHABILITATION PROJECT BEGINS ON AUGUST 27, 2018

PUBLIC NOTIFICATION OF CONSTRUCTION
 COUNTRY CLUB DRIVE & KINGS LANE REHABILITATION
  
PROJECT LOCATION:
COUNTRY CLUB DRIVE BETWEEN LAKESHORE BLVD. AND ARROWHEAD DRIVE, AND KINGS LANE IN CLEARLAKE, CA
  
PROJECT DESCRIPTION:
REPLACEMENT OF SURFACE WITH NEW ASPHALT SURFACING AND ROADWAY IMPROVEMENTS, AND NEW STORM DRAINAGE SYSTEM.
  
PROJECT DURATION:
THE PROJECT IS SCHEDULED FOR CONSTRUCTION AUGUST 27, 2018 TO APPROXIMATELY OCTOBER 15, 2018.
  
HOURS OF CONSTRUCTION:
MONDAY THROUGH SATURDAY 6:00 AM TO 5:00 PM.
  
TRAFFIC CONTROL:
TRAFFIC MAY BE DELAYED DURING HOURS OF CONSTRUCTION.
 
TRAFFIC CONTROLLED BY FLAGMEN AND/ OR CONSTRUCTION TRAFFIC CONTROL DEVICES AND SIGNAGE. ACCESS TO PROJECT SITE IS OFF LIMITS TO PUBLIC.
 
 CONTACT INFORMATION:
PROJECT FOREMAN: Dana Pool (Granite Construction)
PROJECT ENGINEER: John Johnson (Granite Construction) 707 367-5500
 

Address/Location
Clearlake PD
14050 Olympic Dr
Clearlake, CA 95422

Contact
Emergency: 9-1-1
Non-emergencies: 707-994-8251

TEXT-A-TIP -  Text TIP CLEARLAKEPD followed by your message, to 888777

Submit an anonymous web tip

Navigate & Discover