PUBLIC NOTIFICATION OF CONSTRUCTION PINE STREET REHABILITATION PROJECT TO BEGIN ON AUGUST 27, 2018

PUBLIC NOTIFICATION OF CONSTRUCTION
 
PINE STREET REHABILITATION PROJECT
 
PROJECT LOCATION:
PINE STREET BETWEEN DIVISION AVENUE AND OLYMPIC DRIVE IN CLEARLAKE, CA
  
PROJECT DESCRIPTION:
REMOVE AND REPLACE CONCRETE SIDEWALK, CURB AND GUTTER, WITH THE ADDITION OF TWO RAMPS. REMOVAL AND REPLACEMENT OF ROADWAY SURFACING.
 
 PROJECT DURATION:
THE PROJECT IS SCHEDULED FOR CONSTRUCTION AUGUST 27, 2018 TO APPROXIMATELY OCTOBER 15, 2018.
 
 HOURS OF CONSTRUCTION:
MONDAY THROUGH SATURDAY 6:00 AM TO 5:00 PM.
 
TRAFFIC CONTROL:
TRAFFIC MAY BE DELAYED DURING HOURS OF CONSTRUCTION.
 
TRAFFIC CONTROLLED BY FLAGMEN AND/ OR CONSTRUCTION TRAFFIC CONTROL DEVICES AND SIGNAGE. ACCESS TO PROJECT SITE IS OFF LIMITS TO PUBLIC.
 
CONTACT INFORMATION:
PROJECT FOREMAN: Dana Pool (Granite Construction)
PROJECT ENGINEER: John Johnson (Granite Construction) 707 367-5500
 
 

Address/Location
Clearlake PD
14050 Olympic Dr
Clearlake, CA 95422

Contact
Emergency: 9-1-1
Non-emergencies: 707-994-8251

TEXT-A-TIP -  Text TIP CLEARLAKEPD followed by your message, to 888777

Submit an anonymous web tip

Navigate & Discover