Main Street Downtown Milling & Paving
The City of Oneonta will be milling and paving Main St from Chestnut St to Elm St, including side street tie-ins, at night this week. Work will occur between 8:00 p.m. – 7:00 a.m., and is expected to be completed according to the following schedule, weather permitting.
Wednesday, July 12th Mill Main St from Chestnut St to Elm St, including side street tie-ins; Adjust manhole covers; replace traffic signal pavement loops at Chestnut St
Thursday, July 13th Pave Main St from Chestnut St to Elm St, including side street tie-ins; stripe crosswalks and stop bars
During the work, Main St from Chestnut St to Elm St will be closed to all vehicular traffic. As such, there will be no on street parking allowed in the work zone from 6:00 p.m. to 7:00 a.m. each night. Drivers are asked to please comply with all work zone and temporary no parking signage.
In the event that the work is delayed, it will proceed the following night, weather permitting.
For questions, please call the City Engineering Department at 607-432-6465 x3.