Please be Advised that the City's Hot-in-Place Pavement Recycling Project scheduled for 7/19 to 8/12 at various locations with the City.
The City of Norton Shores wishes to notify you that the 2016 Hot-in-Place roadway pavement recycling project is scheduled to start on July 19, 2016 and run until August 12, 2015 (weather dependent). The work will involve several streets in various locations throughout the City. Access and travel thru the affect street will remain open during the work with traffic being controlled by flagging operations and delays are to be expected. The affected streets are as follows:
1) Brookwood Drive, Rood to Cul-de-Sac
2) Cherry Avenue, Thompson to east end
3) Davis Road, Hile to Brookwood
4) Grand Avenue, 290' off Grand Haven to East Byron
5) Oak Hollow Court, Treeline to Cul-de-Sac
6) Summit Avenue, Getty to Bailey
Work on lowering casting to start July 19, 2016.
Work on preparation milling to start July 20, 2016.
Work on Hot-in-Place Recycling to start 1st week of August.
Work on Pavement overlay of Hot in Place to Start 2nd Week of August.