Roadwork on Rt 172 in Bedford Village
MILLING AND PAVING ROUTE 172 Work has started. This is for the stretch from Village Green up to Route 137. Night work will take place on April 21 and 22. Milling and paving will begin on Monday April 25th and last approximately 10 nights (8:00 pm to 6:00 am) weather permitting. No Saturday night. It’s going to be very noisy. Milling and paving will last approximately ten (10) days weather permitting. There will be some closure of single lanes. The remaining contract work will last an additional month.