CAPITAL IMPROVEMENTS PROJECT UPDATES 2010 Water System Rehabilitation Plan

MEADOWS OF SPRINGBROOK SPECIAL ASSESSMENT #112
Meadows of Springbrook will have some additional driveway and restoration work to complete the project. Work should be complete by the end of July.

ZONE CONTROL VALVES
Installation has started on Strathmoor near Saint Anthony Hospital then crews will be moving to Mulford Road just north of East State Street. Traffic patterns and lane closures will occur. Please use extreme caution while driving in this area. The rest of the valves will continue throughout the summer. The project is expected to be complete by the end of November.

MORSAY BRIDGE RHABILITATION
Morsay Drive is closed for bridge construction. The bridge is located on Morsay Drive just east of Fairview Blvd. The bridge is recieving a total deck replacement. Completion is scheduled on September 17, 2010. Please follow the appropriate detours and use extreme caution driving in the area.

KISHWAUKEE ST BRIDGE PROJECT
Crews are working on Kishwaukee Street Bridge Project from Pope Avenue to Buckbee Street. Traffic patterns will be changing due to striping, raised reflective marker installation and parkway restoration. Please use extreme caution while driving in the area.