Springfield Pike Construction Project Update

Week of October 22:
-Finish any remaining concrete work in the north bound curb lane.
-Continue driveway apron replacements.
-Continue pouring new curb and handicap ramps.
-Begin street tree removal on the Pike (trees with pink ribbons will be removed).

There are 37 out of 269 street trees marked to be removed along Springfield Pike. These trees are to be removed because they:
1. Are in the existing curb line and will not survive the project;
2. Are in bad health, and/or
3: Are pear trees (which are unstable and invasive).

Follow this link for information on the Springfield Pike trees:
https://whatsupwyoming.com/2018/10/towards-a-healthier-tree-population/

Week of October 29 
-Replace concrete sidewalk front of businesses.
-Complete any outstanding work remaining in the northbound curb lane from the corporation line to Wilmuth.
-Begin saw cutting the south bound curb lane, plan to start from Jewett and work south.
-Paving begins in the north bound curb lane from south corporation line to Wilmuth.
 

Address/Location
City of Wyoming
800 Oak Ave
Wyoming, OH 45215

Contact
Emergency: 9-1-1
Non-emergencies: 513-821-0141

TEXT-A-TIP -  Text TIP WYOMING followed by your message, to 888777

Submit an anonymous web tip

Navigate & Discover