Springfield Pike Construction Update
Springfield Pike Reconstruction Project Update
Friday, September 7: Remove curb and driveway aprons from Allen to Clark.
The week of September 10: Contractor will be working Monday-Thursday (10 hours per day).
Monday, September 10: Remove curb and driveway aprons from Clark to Walnut.
Tuesday, September 11: Remove curb and driveway aprons from Walnut to just north of the Mt Pleasant intersection.
Wednesday, September 12: Start the full depth removal of roadway in the parking lane from just north of Mt Pleasant working north.
Thursday, September 13: Continue full depth removal working north to Worthington.
Prep work in the open trench for the concrete pour (to be scheduled).
Friday, September 14: Makeup day if lost time due to weather issues.