I-15 South Davis Improvements Project Special Update 11/13/14

I-15 South Davis Improvements
Project Special Update 11/13/14
*The construction activities below are applicable until the next email update.
Add a description


The northbound I-15 Lane Split is now in effect. Please slow down, follow posted signage and get into the right lanes early if you plan to exit at 500 South or 400 North in Bountiful. Through traffic can stay left to avoid ramp congestion.

The lane splits have shifted two lanes of traffic to the inside, and two lanes to the outside of the interstate, creating a work zone in the center. Inside lanes will serve thru-traffic, while the outside lanes will serve the local exits. These lane splits are designed to minimize traffic delays by allowing crews to replace I-15 bridges without closing this important section of interstate highway, and are expected to remain in place through the first week of February.



During this period, the speed limit is reduced to 55 mph in the lane split zones. Drivers are encouraged to pay close attention to electronic message and exit signs and change lanes early enough to safely exit. For northbound I-15, the split will begin between the 2600 South and 500 South interchanges in Bountiful.




The southbound split at 500 South is scheduled for this Friday night, November 14, dry weather permitting.



Construction schedules and dates are subject to change



udot.utah.gov/i15southdavis