South Davis I-15 Construction Update for Oct 16, 2014

I-15 South Davis Improvements
Project Email Update 10/16/14
*The construction activities below are applicable until the next email update.
Add a description


Lane Splits are coming in early November!
In early November, two I-15 traffic lanes will be shifted to the inside of the interstate and two lanes will be shifted to the outside, creating a work zone in the center. The split will be in place in both directions on I-15 between 400 North and 1500 South in Bountiful. The outside lanes will service local exits while the inside lanes will accommodate through traffic. Traffic in the inside lanes cannot access the exits and must continue on I-15 until the next exit. As part of the lane splits, the speed limit will be reduced to 55 MPH, please pay close attention to the signs to give yourself enough time to exit. More info


Upcoming Construction Activities
1500 South

As early as October 20, crews will begin work on the waterline on the north side of 1500 South between 600 West and 675 West. Expect shoulder closures and lane restrictions during the day through mid-November. Flaggers will be present to control traffic. More information about anticipated impacts will be provided as schedules are confirmed.
500 South

As early as October 20, signal and utility relocation will begin at the intersection of 500 South and 500 West. Expect a traffic shift in late October and increased construction activity in the area. Local business access will be maintained.
As early as October 27, crews will shift traffic to the north side of 500 South between I-15 and just east of 500 West to allow room for a work zone on the south side. Expect single lane closures at night.
Construction schedules and dates are subject to change
Ongoing Activities
Expect multiple lane closures on I-15 at night in both directions through October. Single lane closures will begin at 9:00 p.m. with I-15 restricted to one lane in each direction by midnight. These lane closures will be implemented for the bullet points below and other activities including asphalt removal and replacement, concrete pavement rehabilitation, restriping and bridge rehabilitation at multiple locations throughout the project corridor. Area residents can expect an increase in nighttime noise and activity.
Nightly through October, expect roadway removal and paving operations in various locations on I-15 in both directions between I-215 and 500 South.
Expect single lane closures and flagging operations on 1500 South during the day and nighttime hours. Area residents can expect an increase in nighttime noise, dust, vibration, and construction vehicles in the area.
Steel bridge support installation (pile driving) continues at 2600 South through October. This activity is expected to take place during daylight hours. Surrounding residents and businesses can expect an increase in noise and vibration.
Crews continue bridge construction activities on 500 South and 1500 South, and 2600 South near I-15.
Noise wall panel installation continues through early November between 400 North and U.S. 89. Area residents can expect an increase in noise and construction activities at night during this work
Travel lanes are narrowed to 11'.
Per city ordinance, trucks are restricted from using Center Street and Main Street in North Salt Lake as an alternate to 2600 South/1100 North. Trucks should use I-215 as an alternate route.

Project Overview

The I-15 South Davis Improvements project will:

Add ExpressLanes in both directions from the north I-215 interchange to U.S. 89 in Farmington.
Replace aging bridges at 2600 South, 1500 South, 500 South, and 400 North.
Reconfigure the interchanges at 2600 South and 500 South in Bountiful to improve east/west mobility
Improve active transportation with better pedestrian facilities at 500 South, 400 North and Parrish Lane.
Expect single and double lane restrictions on I-15 nightly as early as 7:00 pm and as late as 7:00 am. Actual lane closure times may vary within these hours based on real time traffic numbers.



Periodic rolling traffic slowdowns will also occur at night with the assistance of the Utah Highway Patrol. These slowdowns are conducted to complete construction activities and avoid full closures of the Interstate.



Travel lanes are reduced to 11' wide. Trucks carrying loads wider than 11' should contact the UDOT Motor Carrier Division, 801-965-4892.



I-15 construction is expected to complete in spring 2015 with interchange and bridge construction continuing through summer 2015.



Information about non-UDOT projects in the area is available at the end of this email.

Plan Ahead To Reduce Delays And Impacts

I-15 will remain open without restrictions during peak hours. However, travel delays up to 30 minutes are expected during peak travel times. Use Legacy Parkway or Frontrunner to avoid delay. FrontRunner provides all-day service with 30-min. frequency during peak hours.



Safety

Stay alert and be prepared for changing lane configurations in the project area for your safety and the safety of those working here. Please obey the posted speed and be aware for changing roadway conditions throughout the project area.

Other Projects in the Area

North Salt Lake 1100 North Reconstruction Project (Redwood Road - 110 East)
Construction continues on this project. Please contact 888-427-8585 or [email protected] for more information.



udot.utah.gov/i15southdavis