Woods Cross Police Department
Wednesday July 23rd, 2014 :: 01:39 p.m. MDT

Advisory

An update to this message has been issued.

South Davis County I-15 Update for July 23rd

I-15 South Davis Improvements
Project Email Update 7/23/14
*The construction activities below are applicable until the next email update.


In observance of Pioneer Day, no work affecting travel lanes is scheduled to occur from July 23 at 5:00 a.m. - July 27 at 10:00 p.m. Traffic will remain in the current configuration with lanes narrowed to 11'.


Upcoming Construction Activities

2600 South

The nights of August 1 & 2, portions of the old 2600 South bridge over I-15 will be demolished. 2600 South will be closed to east/west traffic under the bridge from 10:00 p.m. to 5:00 a.m. nightly during demolition. The I-15 interchange will remain open. I-15 traffic can use 500 South and local traffic can use 1500 South as alternate routes. See map below.

2600 South Demolition Alternate Routes


North Salt Lake City has begun a project on 1100 North (2600 South) and will CLOSE the road July 25-August 10. Union Pacific will perform an ADDITIONAL ROAD CLOSURE for track work August 10-14. Expect heavy delays. See the bottom of this email for more information.

Construction schedules and dates are subject to change


Ongoing Activities
Crews continue to rehabilitate the bridge over Center Street and Main Street in North Salt Lake. Area residents may experience an increase in light, noise, and vehicle activity associated with this work.
Night paving is ongoing on the west side of I-15 between 2600 South and 500 South through July and on the east side of I-15 between 2600 South and Pages Lane through early August.
Median reconstruction between Parrish Lane and the northern project limits is ongoing through August.
Crews continue roadway widening activities in the shoulders between I-215 and Pages Lane during the day and at night on both sides of I-15. Area residents may experience an increase in light, noise, and vehicle activity associated with this work.
Crews continue construction activities on 500 South near I-15 including soil stabilization efforts for the new bridge.
Bridge work continues at 500 South and 1500 South.
Travel lanes are narrowed to 11'.

Project Overview

The I-15 South Davis Improvements project will:

Add ExpressLanes in both directions from the north I-215 interchange to U.S. 89 in Farmington.
Replace aging bridges at 2600 South, 1500 South, 500 South, and 400 North.
Reconfigure the interchanges at 2600 South and 500 South in Bountiful to improve east/west mobility
Improve active transportation with better pedestrian facilities at 500 South, 400 North and Parrish Lane.
Expect single and double lane restrictions on I-15 nightly as early as 7:00 pm and as late as 7:00 am. Actual lane closure times may vary within these hours based on real time traffic numbers.



Periodic rolling traffic slowdowns will also occur at night with the assistance of the Utah Highway Patrol. These slowdowns are conducted to complete construction activities and avoid full closures of the Interstate.



Travel lanes are reduced to 11' wide. Trucks carrying loads wider than 11' should contact the UDOT Motor Carrier Division, 801-965-4892.



I-15 construction is expected to complete in spring 2015 with interchange and bridge construction continuing through summer 2015.



Information about non-UDOT projects in the area is available at the end of this email.

Plan Ahead To Reduce Delays And Impacts

I-15 will remain open without restrictions during peak hours. However, travel delays up to 30 minutes are expected during peak travel times. Use Legacy Parkway or Frontrunner to avoid delay. FrontRunner provides all-day service with 30-min. frequency during peak hours.



Safety

Stay alert and be prepared for changing lane configurations in the project area for your safety and the safety of those working here. Please obey the posted speed and be aware for changing roadway conditions throughout the project area.

Other Projects in the Area

North Salt Lake 1100 North Reconstruction Project (Redwood Road - 110 East)
There will be a complete road closure (no traffic in either direction) at the railroad tracks east of Main Street, July 25th - August 10th. Please use Pacific Avenue as an alternate route during those dates (see detour map below).
UPPR closure at the railroad tracks east of Main Street.
From August 10th to August 14th, Union Pacific Rail Road will be removing and installing new train crossing panels. UPRR is replacing their crossing panels which will create a smoother road for the City. Please use Pacific Avenue as an alternate route during the UPPR Road Closure (see same detour map below).

Contact 888-427-8585 or [email protected] for more information.