I-405 Sepulveda Pass Improvements Project
Monday March 1st, 2010 :: 11:39 a.m. PST

Advisory

Overhead power lines on Sepulveda Blvd. will be relocated beginning March 1 and continuing for eight weeks.

As part of the I-405 Sepulveda Pass Widening Project and in preparation for the relocation of Sepulveda Bl to the east, the Contractor, in conjunction with LADWP, will relocate the overhead power lines on Sepulveda Blvd. between Montana Ave. and Sunset Blvd. The work will begin March 1 and continue for eight weeks, weather permitting.

For the most recent road closure information, please visit metro.net/I-405.